Progress Report > Package III - Electrical Works

As of November 30, 2004

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

14 February 2003

Contract Period 26 months (Until April 13, 2005)
Time Elapsed (days)  647 of 780 (82.95%) Remaining 133 days

Progress

 

Installation of fire rated (FR) cable, supply cables for CCTV cameras, complete the installation work for area lighting floodlighting towers in NPP and NTP. Conduit was installed in sub-base at NPP and SPP for area lighting circuits.

Photographs

 

MV Cable Pulling Work at Main Tunnel

Traffic Loop Installation

Traffic Loop Installation

Excavation for Road Lighting Foundation at North Road

Lighting Pole Installation at South Bridge

Excavation for Lighting Pole Foundation at South Road

Lighting Installation at South Tunnel Portal

S/S5 Equipment Installation Work

Top

Construction Supervision

Summary from Contractor

The Contractor's site construction progress for the month of November was slower than desirable because access to substation buildings was delayed to the later part of the month and because of rain delays to outside works. Some low voltage equipment and supports was installed in S/S#5 and installation of 22kV switchgear (GIS) began in S/S#6 (VAB). Installation of road lighting pole foundations along the south road continues. A small amount of lighting and small power works in the VMB and toll plaza buildings was done. Tunnel overhead works were limited to cable ladder crossings at EP and VAC intersections with main tunnel, installation of brackets for the support of radio rebroadcast (RRB) coaxial antenna, fire sensor cable, and CCTV camera supports.

Substation No 6  (S/S#6) at the VAB was turned over to PKIII from PKIV in late November.  S/S#5 was turned over in early August and OCC, S/S#7 and 8 have been available since April 2004. S/S#1 was turned over at the beginning of December.

Medium voltage (MV) cable pulling began at the end of October in the main tunnel and continues in the ventilation adit and on Lang Co bridge. Conduit and boxes continue to be installed in VAB as PKIV work progresses.

Design work at site continues on the preparation and submittal of installation shop drawings. Detailed design continued in ABB Finland on systems (Fire alarm, and radio rebroadcast (RRB).  Factory acceptance tests (FAT) were completed in early October in Finland on traffic control, lighting control, power distribution control, and main SCADA systems and on systems integration.

PKIII took over maintenance of PKV works as provided for under their contract in May and were to negotiate to sub-contracted this work to HAMADECO. However HAMADECO declined to sign PKIII sub-contract agreement citing unacceptable insurance clauses.  These clauses were copied from PKIII contract documents. PKIII will continue with maintenance of PKV works without sub-contractor.

Construction Supervision

Cable Pulling of Main Tunnel Lighting has been completed on the raceways.

Power Cable Pulling for Main Tunnel CCTV has been completed on the raceways.

Low Voltage cabling work at VMB has continued.

Low Voltage cabling work at S/S 5 has continued.

Lightning Protection System work at S/S 5 has completed.

Foundation for area lighting at NPP and NTP has been completed.

Low Voltage cabling work at STP has started

Building luminaries Installation work at STP has started.

Piping and Box Installation work at VAB has continued.

Cable trench excavation work for area lighting have been completed at SPP and NPP.

Batteries have been installed at SS5 and OCC

UPS have been installed at OCC

Installation of UPS, inverters and chargers have started in SS5.

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination