Progress Report > Package IB - South Tunnel Section
Main Tunnel and Evacuation Tunnel excavation was completely finished. Bench excavation and tunnel lining were completed. The rear concrete works is ongoing. Construction Supervision by Engineer Cut and Cover Section Construction for cut and cover section continued. Riprap of cut and cover section continued 240 m2 South Portal Plaza a. Concrete curb 246ml b. Granit curb 205ml c. Construction of Sub base layer 1+2 500m3 Main Tunnel Rear Work Finished Road
work Profile line marking at roadway 2423ml Rubber guard cone 133 piece Stainless steel revision shaft cover 56 piece Evacuation Tunnel Rear Work Construction of penetration layer 1500ml Construction of concrete pavement 160ml Major Events and Issues This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||||