Progress Report > Package IB - South Tunnel Section
Main Tunnel and Evacuation Tunnel excavation was completely finished. Bench excavation and tunnel lining were completed. The rear concrete works is ongoing. Construction Supervision by Engineer Cut and Cover Section Construction for cut and cover section continued. Riprap of cut and cover section continued 240 m2 South Portal Plaza a. Concrete curb 150ml b. Construction of Sub base layer 1+2 3400m3 c. Construction of Base layer 1 6800m3 Main Tunnel Rear Work Finished Road
work Concrete pavement cross passage door: 2(nos) Concrete wall for door: 1(nos) Tunnel lining painting West side : 323 (ml). Total 2423/2423(ml) and completed. Tunnel lining painting East side : 200 (ml). Total 500/2423(ml) and on going. Installation of hand rail : 410 (ml). Total 2423/2423(ml) and completed. Evacuation Tunnel Rear Work Construction of base layer 2 1000ml. Major Events and Issues This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||||