Progress Report > Package IB - South Tunnel Section
Main Tunnel and Evacuation Tunnel excavation was completely finished. Bench excavation and tunnel lining were completed. The rear concrete works is ongoing. Construction Supervision by Engineer Cut and Cover Section Construction for cut and cover section continued. Support Shotcrete for slope 350 m2 South Portal Plaza a. Surface ditch 280ml b. Concrete curb 50ml c. Construction of Sub base layer 1 4130m3 d. Construction of Sub base layer 2 1728m3 Main Tunnel Rear Work Finished Road
work Concrete pavement West side : 1320 (ml). Total 2423/2423(ml).and completed Tunnel lining painting West side : 0 (ml). Total 2100/2423(ml) and temporary stop works. Tunnel lining painting East side : 0 (ml). Total 300/2423(ml) and temporary stop works. Installation of hand rail : 1200 (ml). Total 1950/2423(ml) Evacuation Tunnel Rear Work Construction of base layer 1 2275ml. Construction for cut and cover section continued. Support
Shotcrete for slope
350 m2 Major Events and Issues This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||||