As of July 31, 2004

Physical Progress

Contractor

JV of Dong Ah and Song Da

Commencement of the Works

1st October 2000

Contract Period

1460 days (Until September 30, 2004)

Time Elapsed (days)

1380 of 1460 (94.52%) Remaining 80days

Progress

 

Main Tunnel(2417m)

Excavated 2379m in total (100%)

Evacuation Tunnel(2429m)

Excavated 2411m in total (100%)

Access Road to Water Reservoir.

Completed

Bridge No.1(58m)

Complete the concrete placement and concrete at two ends of bridge approach slab.

Others

 

 

Photographs

South Tunnel Portal Plaza
Inspection of Electric System
Construction of Concrete Pavement
Griding to Repair the Surface of Pavement

Top

Construction Supervision

Summary from Contractor

Main Tunnel and Evacuation Tunnel excavation was completely finished. Bench excavation and tunnel lining were completed. The rear concrete works is ongoing.

Construction Supervision by Engineer

Cut and Cover Section

Construction for cut and cover section continued.

Support Shotcrete for slope                                     350 m2    

  • South Portal

Electric system

At present, They had handed-over electric system of South tunnel portal plaza on 09/07/2004.

Water system

Until now, They have completed all Drainage manhole, West surface ditch

At present, They are continuing to construct the pipe system, leach field (Type A, B), East surface ditch

Main Tunnel Rear Work

Finished

Road work

Concrete pavement East side: 1161 (ml).Total 2423/2423(ml) and completed.

Concrete pavement West side: 1320 (ml).Total 1320/2423(ml).

Tunnel lining painting West side: 0 (ml). Total 2100/2423(ml) and temporary stop works.

Tunnel lining painting East side: 0 (ml). Total 300/2423(ml) and temporary stop works.

Installation of hand rail: 600 (ml). Total 850/2423(ml)

Evacuation Tunnel Rear Work

Placement side drain: 435 (ml). Total 2435/2435(ml) and completed

Major Events and Issues

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination