As of June 30, 2004

Physical Progress

Contractor

JV of Hazama and Cienco 6

Commencement of the Works

1st October 2000

Contract period

1460 days (Until September 30, 2004)

Time Elapsed (days)

1350 of 1460 (92.46%) Remaining 110 days

Progress

 

Main Tunnel(3857m)

Excavated 3857m in total (100%)

Concrete Lining: 3,847.00m (99.99%)

Evacuation Tunnel(3857m)

Excavated 3857m in total (100%)

Cast concrete for Side Drainage completed 3,847m

Ventilation Tunnel(1810m)

Excavated 1887.62m in total (100%)

Concrete Lining: 1,887.62m (100%)

Others

 

Photographs

Main Tunnel
Main Tunnel Cut & Cover Setting of Rebar
North Portal Plaza Enlargement Chipping of Boulders
Sub-Station No.5 Front Elevation Brick Laying
Main Tunnel Cut & Cover Section Stripping of Form
Main Tunnel Concrete Payment (East Side) Sta. 3+586 to 3+406
Pedestrian Cross Passage No.3 Setting of Wood Form
Adit Portal
Ventilation Adit Partition wall Base Part - Blk. 179
Ventilation Adit Partition Wall Part - Blk. 121
Ventilation Adit Base Course Blk. 90-95 - RT. Side
Ventilation Adit Partition Wall Sliding Steel Form Installation - Left Side

Top

Construction Supervision

Summary from Contractor

The Concrete Lining for Standard Section of the Main Tunnel completed 3,847.00m (progress 99.99%), and the remaining, cut and cover part, is anticipated to complete in next month.

In the Evacuation Tunnel, the casting of he side drainage slab cover was on going at part No.1 of Grp#1 at Sta 2+955 - Sta: 5+500, Grp#2 at Sta 1+653 - Sta 1+807. The casting of side drainage slab cover for side drainage completed this month giving a total length of 2699.00 meters.

The Ventilation Adit Concrete Lining completed on April 21, 2004.

Construction Supervision by Engineer

Main Tunnel 

Main Tunnel Rear Works (Concrete Works)

The Main Tunnel Concrete Lining completed up to the end of April month totaled to 3,847.00m (Progress: 99.99%). The remaining L= 10m ( Portal cut and cover part), will be finished next month.

  • East Side: (Left Side)

Cable Duct Bank:

Completed on 30/4/2004 with total length 3,847.00m. the remaining L=10m(Portal cut and cover section).

Side Drainage/Catch Basin:

Completed on 30/4/2004 with total length 3,847.00m. the remaining L=10m(Portal cut and cover section)

  • West Side: (Right Side)

Cable Duct Bank:

The conduit duct bank concreting under the walkway structure has been commenced from station 1+691.55 and reached to station 5+500, giving a length of 3,808.45m.

Side Drainage/Catch Basin:

Completed on 30/4/2004 with total length 3,847.00m, the remaining L=10(Potal cut and cover section).

  • Walkway Structure:

The base concreting works has been completed from station 1+669.70 to station 5+160.0m and from station 5+260 to station 5+500, totaling a length of 3,730.3m. Concreting of sidewall was also started on the same station and reached to station 5+160.0 and from station 5+206 to station 5+500.00 with a total length 3,730.3m. The casting concrete of hydrant pipe saddle inside the walkway structure was also simultaneously executed with a base concrete starting from the same station and reaching to station 5+500  totaling 3,830.3m.

On May 20, 2004, a joint site inspection between the Consultant and contractors Package IA, III and IV was held prior to handing over. The west side walkway structure was transferred by PKIA to III/IV and east side duct bank to PKIII both Zone I and J1 from station 4+910 to Station 5+470 though it was agreed that some minor items were needed to correct on both sides.

  • Main Drainage:

Completed from Station 1+653 – Station 5+500 totaled to 3,847metters, the maining L= 10m ( Portal cut and cover section).

  • MT Road Works

Sub-grade:

This month of May 2004, the contractor had no schedule for performing proof rolling test for sub-grade. The approved area from previous month started from station 1+770 until station 5+500 with a total length of 3,730.0meters.(Progress:99%).

Base Course:

The contractor Cienco 6 continues to carry out the spreading of the first and second layers of the base course and its compaction starting from station 1+780 to 5+500 of both sides. Prior to the second layer spreading, the Engineer requires the contractor to perform field density test at every 200meters distance per point for quality checking and to follow the requirement of Technical Specifications, Section 02580-Aggregate Sub-base and Base Course. The Field Density Test for the first layer has a good result. This month, the FDT for the second layer was also performed and has a good rate for the compaction test and moisture rating content. The Engineer also instructs  the contractor to conduct Benkelman Test with electro-mechanical measuring device from/conducted by Danang Laboratory for the final second layer of base course.

All testing of base course materials has been performed at Danang Laboratory with the presence of Consultant Engineer and that materials test results were satisfactory passed and accepted by the Engineer, The remaining 137.0 metters

  • Pavement works

West side (Right side):

The concrete pavement for standard section of the Main tunnel, was started from station 1+802 to station 5+500 totaling 2600meters. The concrete pavement works for Lay-by Right side No. 2,4,6,8,9,11 with a length of 174 metters were completed.

East side: (Left side)

The concrete pavement for standard section of the Main tunnel, was started from station 3+430.00 – 5+500.00 totaling 2070.0 metters. The concrete pavement works for Lay-by Left side No. 7,10 with a length of 58 metters were completed.

  • Electrostatic Precipitator No. 2:

Completed and Handed over to PKIII& PKIV on Mar 31,2004.

Evacuation Tunnel

The casting of concrete for the Side Drainage completed from Sta:1+653 – Sta:5+500 giving a  total length of 3,847 meters, remaining 10 meters ( Portal cut and cover section).

Side drainage slab cover: The casting of the side drainage slab cover was on going at part No. 1 of Grp #1at Sta 2+955 – Sta: 5+500, Grp# 2 at Sta 1+653 – Sta:1+807. The casting of side drainage slab cover for side drainage completed this month giving a total length of 2699.00 metters.

ET Road works:

Subgrade: was started from station:4+870.0 – 5+500.0 with totaling of 630.0 metters

Cross Passage:

The casting of concrete for cross passage doors  completed No.2,3,4

Ventilation Adit Tunnel

  • Concreting Works:

Cut and Cover Section / Connection Lining Concrete at Portal:

The Concrete Lining for Cut and Cover Section, with Portal Wall, and two (2) blocks of Normal Section of Lining Concrete connecting to the Cut and Cover Section were completed with a total length of 13.97m from Station 1+738.54 to 1+752.51.

Lining Concrete:

The Ventilation Adit Concrete Lining completed on Apr 21,2004, including Cut and Cover Section together with its connection to the normal section and enlargement section, Totaled to 1,887.62m (Progress: 100%).

  • Rear Works:

Main Drainage:

The installation of 300mm dia. Perforated Concrete Pipe had been started at station 0-066.83 and, this month, reached to station 1+752.51 with total length of 1,819.34 metters including setting/connection of pre-cast concrete manhole No.1 at the bottom part of VA intersection of Exhaust Shaft Section.

Center Wall Concrete:

Construction of foundation together with the first lift 0.60m of the center wall had been started at station 0-071.05 and this month reached to station 1+714.64, totaling 1,785.69metters.

The second lift Center Wall commenced at the bottom VA station -071.05 and reached to 1+192.77 with a total length for Form No.1 and 2 is  1,263.82metters.

Cable Duct Bank: Completed on Apr 29,04).

Subgrade of Road:

The contractor carried out the spreading of the Subgrade and its compaction Starting from Station – 71.05 to 0+874.12 of Right side with total length  of 945.17 metters.

Base – course of Road:

Starting from Station - 19.05 to 0+874.12 of Right side with Total length of 883.17 meters.

Pavement works:

The contractor carried out pouring concrete pavement starting from station 0-65.05 – 0+447.72 of Right side with totaling of 512.77 meters.

Safety at Work:

At 11h on June 24,2004 while transferring form for concreting work of partition wall, a worker was killed by suddenly slid form. The reason and consequence of the accident have been stated in detail at the meeting with the Consultant and the Employer right after that on June 25,2004.

Conclusion: The Contractor proposed countermeasures to ensure safety in concreting work, especially in form move which was accepted by the Consultant. At present, concreting work of partition wall has been executed ordinarily.

Major Events and Issue

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination