Construction Supervision All main works of Lien Chieu Substation for VO No. 1 was completed in May with the exception of some communications tests and SCADA adjustments. Meetings variously between PMU85, PTC No. 2, Engineer, and the Contractor continued to be held during May to coordinate the requirements for the energisation of the Hai Van Pass Tunnel 110kV substation. The actual energisation and duration (whether 72 hours trial energisation or permanent service) is dependant on EVN concurrence and a final determination of which parties will be responsible for operations and maintenance of what sections of the PKV installed power system. At month's end it was clarified that PTC No. 2 would operate and maintain the high voltage substation and transmission line for 12 months under contract to HAMADECO after permanent energisation. A tentative date for SITOC inspection and test energisation was set as 15 May 2004. A joint inspection was carried out on 1st April of all non-electrical items on snag lists. There were a small number of outstanding items that have been corrected. An official Turning - Over ceremony was held in April of the PKV works. This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||