Welcome to Our Site!
 

 

As of May 31,2004 

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

21 December 2001

Contract period

540 days (Until June 20, 2003)

Time Elapsed (days)

880 of 540 (162.96%) Extended from June 20, 2003

Progress

 

 

- All main works of Lien Chieu Substation for VO No. 1 completed.

Photographs

Top

Construction Supervision

All main works of Lien Chieu Substation for VO No. 1 was completed in May with the exception of some communications tests and SCADA adjustments. Meetings variously between PMU85, PTC No. 2, Engineer, and the Contractor continued to be held during May to coordinate the requirements for the energisation of the Hai Van Pass Tunnel 110kV substation.

The actual energisation and duration (whether 72 hours trial energisation or permanent service) is dependant on EVN concurrence and a final determination of which parties will be responsible for operations and maintenance of what sections of the PKV installed power system.  At month's end it was clarified that PTC No. 2 would operate and maintain the high voltage substation and transmission line for 12 months under contract to HAMADECO after permanent energisation. A tentative date for SITOC inspection and test energisation was set as 15 May 2004.

A joint inspection was carried out on 1st April of all non-electrical items on snag lists. There were a small number of outstanding items that have been corrected.

An official Turning - Over ceremony was held in April of the PKV works.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination