As of March 31, 2004

Physical Progress

Contractor

Matsushita - Itochu Consortium

Commencement of the Works

13 March 2002

Contract period 1080 days (Until March 12, 2005)
Time Elapsed (days) 738 of 1080 (68.33%) Remaining 342 days

Progress

 

- Continue the installation for water piping for Water Supply and Treatment System in main tunnel

- Place the based concrete for High Level Reservoir

Photographs

Installation of Air Inlet Side Wall for EP1
Ceiling Work for EP3
Backfilling - Foundation Work for Ventilation Adit Building
Concrete Placing for Beams
Installation of Reiforcing Steel for Chimney
Brick Work

Top

Construction Supervision

Summary

Water Supply and Treatment System:

Reinforcing steel bars for High Level Reservoir installed.

Hydrant piping installation in the main tunnel started.

Tunnel Ventilation System:

Start the building works of ceiling for EP1 and EP3

EP and auxiliary machines for EP1 & EP3, Supply/Exhaust fans, EP control equipment were impoprted and stored at the warehouse in Danang.

Ventilation Adit Building

Continue the concrete placing for beams.

Construction Supervision

Permanent work

Water Supply and Treatment System

Installation of water piping in main tunnel progressed as follows:

- Marking   897m      Zone F (Mar 15~20)

            Zone K, J2 (Mar 23~25)

- Anchoring   932m      Zone F (Mar 13~20)

            Zone L (Mar 1~4), K (Mar 28~31)

- Piping   424m   Zone E (Mar 1~6), F (Mar 23~29)

            Zone L (Mar 4~9)

- Pressure test   773m   Zone C (Feb 26~Mar 9), D (Mar 10~15)

            Zone E (Mar 16~)

Tunnel Ventilation System

EP1 & EP3         Structural work of ceiling including installation of Inlet side wall and Separation wall started.

Ventilation equipment are imported and kept at warehouse in Danang

EP units and Auxiliary machines for EP3

EP control panel for EP1 & EP3

Ventilation Adit Building

Concrete is placed for

Beams                    Mar 3, 9, 15

Footings                  Mar 5, 9

Chimney                 Mar 9

Lean Concrete        Mar 8

Slabs                      Mar 9, 15, 24

Pit slabs                  Mar 20

Pit walls                  Mar 24, 27

Ventilation Adit Connection

Making Design Work

Joint Inspections for Taking Over

Walkway pit:      Mar 19   Zone F (North), Mar 29 Re-inspection

Mar 19     Zone K, J2 (South)

Top

Previous month

This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination