Welcome to Our Site!
 

As of February 28, 2004

Physical Progress

Contractor

Matsushita - Itochu Consortium

Commencement of the Works

13 March 2002

Contract period 1080 days (Until March 12, 2005)
Time Elapsed (days) 708 of 1080 (65.55%) Remaining 372 days

Progress

 
 

- Start the hydrant piping installation in the main tunnel and building work for EP1 & EP3.

Photographs

Construction Materials at EP3 (February 21)
Visual Inspection for Construction Materials for EP3 (February 23)
Formwork & Concrete Placing for Base Concrete of High Level Reservoir
Foundation Works for Ventilation Adit Building: Concrete Placing for Beams

Top

Construction Supervision

Summary

Water Supply and Treatment System:

Reinforcing steel bars for High Level Reservoir installed.

Hydrant piping installation in the main tunnel started.

Tunnel Ventilation System:

Start the building works for EP1 and EP3

EP and auxiliary machines for EP1 and Supply/Exhaust were impoprted from Japan.

Ventilation Adit Building

Start concrete placing for beams.

Construction Supervision

Permanent work

Water Supply and Treatment System

Base concrete was placed for High Level Reservoir

Installation of water piping in main tunnel progressed as follows:

          Supports anchoring           3,627m

          Pipe installation           4,166m

          Pressure Test     773m

Tunnel Ventilation System

Shop drawings for machinery of Ventilation System were approved.

Building work for EP1 and EP3 started

Following the Ventilation Equipment were imported and kept in the warehouse in Danang: EP and auxiliary machines for EP1, supply and exhaust fans.

Fabrication of steel structures for EP stations started.

Ventilation Adit Building

Foundation work progressed to concrete placing for beams.

Temporary works

Temporary power supply facilities for EP1, 2, 3 and VAC were provided.

Top

Previous month / Next month

This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination