Contractor
|
Matsushita
- Itochu Consortium
|
Commencement
of the Works
|
13
March 2002
|
Contract
period |
1080
days (Until March 12, 2005) |
Time
Elapsed (days) |
708 of 1080 (65.55%) Remaining
372 days |
Progress
|
|
|
- Start the
hydrant piping installation in the main tunnel and building
work for EP1 & EP3.
|
Photographs
 |
Construction
Materials at EP3 (February 21)
|
 |
Visual
Inspection for Construction Materials for EP3 (February
23)
|
 |
Formwork
& Concrete Placing for Base Concrete of High Level
Reservoir
|
 |
Foundation
Works for Ventilation Adit Building: Concrete Placing
for Beams
|
Summary
Water
Supply and Treatment System:
Reinforcing
steel bars for High Level Reservoir installed.
Hydrant
piping installation in the main tunnel started.
Tunnel
Ventilation System:
Start
the building works for EP1 and EP3
EP and
auxiliary machines for EP1 and Supply/Exhaust were impoprted from
Japan.
Ventilation
Adit Building
Start
concrete placing for beams.
Construction
Supervision
Permanent
work
Water Supply and Treatment System
Base
concrete was placed for High Level Reservoir
Installation
of water piping in main tunnel progressed as follows:
Supports anchoring
3,627m
Pipe installation
4,166m
Pressure Test 773m
Tunnel Ventilation System
Shop
drawings for machinery of Ventilation System were approved.
Building
work for EP1 and EP3 started
Following
the Ventilation Equipment were imported and kept in the warehouse in
Danang: EP and auxiliary machines for EP1, supply and exhaust fans.
Fabrication
of steel structures for EP stations started.
Ventilation Adit Building
Foundation
work progressed to concrete placing for beams.
Temporary
works
Temporary
power supply facilities for EP1, 2, 3 and VAC were provided.
Top
|