Contractor
|
Matsushita
- Itochu Consortium
|
Commencement
of the Works
|
13
March 2002
|
Contract
period |
1080
days (Until March 12, 2005) |
Time
Elapsed (days) |
678
of 1080 (62.77%) Remaining 402 days |
Progress
|
|
|
-
Continued the installation work for water piping in the
main tunnel and fabrication of steel structures for EP
Stations. |
Summary
Water
Supply and Treatment System:
Reinforcing
steel bars for High Level Reservoir installed.
Hydrant
piping installation in the main tunnel started.
Tunnel
Ventilation System:
Anchoring
work was finished for EP1 and EP3
EP
and auxiliary machines for EP1 and Exhaust were impoprted from Japan.
Ventilation
Adit Building
Concrete
placing for footings and columns started.
Construction
Supervision
Permanent
work
Water Supply and Treatment System
Sub
base concrete was placed for High Level Reservoir
Installation
of water piping in main tunnel progressed as follows:
Supports anchoring
2,637m
Pipe installation
2,342m
Tunnel Ventilation System
Shop
drawings for machinery of Ventilation System were approved.
Anchoring
work for EP1 and EP3 was completed.
EP
and auxilliary machines for EP1 and exhaust fans were imported and
kept in the warehouse in Danang
Fabrication
of steel structures for EP1 started.
Ventilation Adit Building
Foundation
work progressed as follows:
Lean
concrete placing (19/38)
Concrete
placing for footings (18/38)
Concrete
placing for columns (9/38)
Top
|