As of December 31, 2002

Physical Progress

Contractor

Matsushita - Itochu Consortium

Commencement of the Works

13 March 2002

Contract period 1080 days (Until March 12, 2005)
Time Elapsed (days) 648 of 1080 (60%) Remaining 432 days

Progress

 
  - Placed subbase concrete for High Level Reservoir and started installation work for water piping and fabrication of steel structures.

Photographs

Concrete Placing for Sub Base of HLR (Dec 24)
Concrete Placing for Footings (Dec 1)
Steel Bar Assembling (Dec 3)
Concrete Placing for Column (Dec 17)
Fixed Point View (Dec 11)
Excavation for MF1 (Dec 31)
Safety Patrol at VAC (Dec 31)
Shop Assembly of EP Fan Pedestal (Dec 19)
Shop Assembly of EP Fan Pedestal (Dec 19)
Concrete Compression Test After 7 days for HLR at the Laboratory of PK1B (Dec 31)

Top

Construction Supervision

Summary

Water Supply and Treatment System:

Concrete placing for High Level Reservoir started

Hydrant piping installation in the main tunnel started.

Tunnel Ventilation System:

Anchoring work was finished for EP1 and started for EP3

EP and auxiliary machines for EP1 were imported from Japan.

Ventilation Adit Building

Concrete placing for footings and columns started.

Construction Supervision

Permanent work

Water Supply and Treatment System

Sub base concrete is placed for High Level Reservoir

Installation of water piping in main tunnel progressed as follows:

Supports anchoring 2,149m

Pipe installation 2,142m

Tunnel Ventilation System

Shop drawings for machinery of Ventilation System were approved.

Anchoring work for EP1 completed.

EP and auxilliary machines for EP1 were imported and kept in the warehouse in Danang

Fabrication of steel structures for EP1 started.

Ventilation Adit Building

Foundation work progressed as follows:

Lean concrete placing (18/38)

Concrete placing for footings (17/38)

Concrete placing for columns (9/38).

Top

Previous month / Next month

This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination