Contractor
|
Matsushita
- Itochu Consortium
|
Commencement
of the Works
|
13
March 2002
|
Contract
period |
1080
days (Until March 12, 2005) |
Time
Elapsed (days) |
648
of 1080 (60%) Remaining 432 days |
Progress
|
|
|
- Placed subbase concrete for High Level Reservoir and
started installation work for water piping and fabrication
of steel structures. |
Photographs
 |
Concrete
Placing for Sub Base of HLR (Dec 24)
|
 |
Concrete
Placing for Footings (Dec 1)
|
 |
Steel
Bar Assembling (Dec 3)
|
 |
Concrete
Placing for Column (Dec 17)
|
 |
Fixed
Point View (Dec 11)
|
 |
Excavation
for MF1 (Dec 31)
|
 |
Safety
Patrol at VAC (Dec 31)
|
 |
Shop
Assembly of EP Fan Pedestal (Dec 19)
|
 |
Shop
Assembly of EP Fan Pedestal (Dec 19)
|
 |
Concrete
Compression Test After 7 days for HLR at the Laboratory
of PK1B (Dec 31)
|
Summary
Water
Supply and Treatment System:
Concrete
placing for High Level Reservoir started
Hydrant
piping installation in the main tunnel started.
Tunnel
Ventilation System:
Anchoring
work was finished for EP1 and started for EP3
EP and
auxiliary machines for EP1 were imported from Japan.
Ventilation
Adit Building
Concrete
placing for footings and columns started.
Construction
Supervision
Permanent
work
Water Supply and Treatment System
Sub base
concrete is placed for High Level Reservoir
Installation
of water piping in main tunnel progressed as follows:
Supports
anchoring 2,149m
Pipe
installation 2,142m
Tunnel Ventilation System
Shop
drawings for machinery of Ventilation System were approved.
Anchoring
work for EP1 completed.
EP and
auxilliary machines for EP1 were imported and kept in the warehouse
in Danang
Fabrication
of steel structures for EP1 started.
Ventilation Adit Building
Foundation
work progressed as follows:
Lean
concrete placing (18/38)
Concrete
placing for footings (17/38)
Concrete
placing for columns (9/38).
Top
|