As of February 28, 2004

Physical Progress

Contractor

JV of Dong Ah and Song Da

Commencement of the Works

1st October 2000

Contract Period

1460 days (Until September 30, 2004)

Time Elapsed (days)

1230 of 1460 (84.24%) Remaining 230days

Progress

 

Main Tunnel(2417m)

Excavated 2379m in total (100%)

Evacuation Tunnel(2429m)

Excavated 2411m in total (100%)

Access Road to Water Reservoir.

Completed

Bridge No.1(58m)

Continued with placement of concrete for cross beam and slab reinforcement.

Others

 

 

Photographs

South Tunnel Portal
Installation of Formwork for Side Drain on West Side
Installation of Formwork for Walkway Pedestrians
Installation of Formwork for Cover Concrete
Embankment Soil and Grassing
Compaction of Backfill Material for Cut and Cover Section
Placement of Concrete Pavement for Bridge No.1
Installation of Reinforcement Steel for Handrail of Bridge No.1

Top

Construction Supervision

Summary from Contractor

Main Tunnel and Evacuation Tunnel excavation was completely finished.

Bench excavation and tunnel lining were completed.

The rear concrete works is ongoing.

Construction Supervision by Engineer

Cut and Cover Section

Construction of cut and cover section continued.

The items carried out during the month can be quantified as follows:

                    Rock gabions:                                             80 nos

                    Structural embankment:                          1750 m3

Tunnel Lining

Backfill grouting for concrete lining from block No. 169 to block No. 181

Quantity cement: 4065 kg

Placement of concrete for side drain: 181.5 m (East side); 207.5 m (West side)

Placement of concrete for cable duct: (East side) 150.1m and cable trough - (West side) 450.0m

Placement of concrete for construction of centre drain 434.0m

Bridge No. 1

Continued with placement of concrete for cross beam and slab reinforcement.

Major Events and Issues

Previous month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination