Progress Report > Package III - Electrical Works

As of January 31, 2004

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

14 February 2003

Contract Period 26 months (Until April 13, 2005)
Time Elapsed (days)  347 of 780 (44.48%) Remaining 433days

Progress

 

- Continue duct bank and hand hole installation at Southern and Northern Toll Plaza.

 

Photographs

NTP Building Ductbank Piping Inspection
NTP Ductbank Piping Installation
NTP Hand Hole Installation
NTP Hand Hole Installation
STP Toll Gate Slab Piping Work - 1
STP Toll Gate Slab Piping Work - 2
Foundation Inspection for Lang Co Bridge
Foundation Inspection for Lang Co Bridge

Top

Construction Supervision

The Contractor continued with electrical works installations in North and South Toll Plaza buildings. The civil works at STP proceeds at very slow pace. The majority of work at site is the preparation and submittal of installation shop drawings. Detailed design continues in ABB Finland on systems (Fire alarm, communications, radio rebroadcast, traffic control, lighting control and main SCADA systems) and systems integration.

PKIII continues to participate in the hand over of sections of walkways in the tunnel from the civil contractors. The hand over allows PKIII (and PKIV) access to install conduit in the trench under the walkways. This conduit work was scheduled to start 2 January, 2004 but because of lack of materials will begin in February.

Coordination is still ongoing between PKIII and PKIV for space, ventilation and cableway requirements at substations in the Electrostatic Precipitator areas (S/S 1, 2 and 4) and at the Ventilation Adit Building (S/S 6), S/S 3 at adit fresh air discharge near tunnel. Generally most significant issues have been resolved between PKIII and PKIV in those areas. The substation layout for construction at the north portal plaza, S/S#5, has been handed over to PK1A. PK1A is responsible for construction of that substation.

The Engineer identified the North and South portal plaza areas as critical civil construction areas to enable early installation of main electrical cables and early supply of power for ventilation fan testing.

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination