![]() |
|||||||||||||||||
|
Welcome to Our Site! |
|||||||||||||||||
|
Construction Supervision From Consultant Engineer Painting inside the building 85 % completed. Floor granite tiles tile 100 % completed. Door installation 100% completed. Window installation 100% completed. Water proofing work on the roof 100% completed. Air-condition installation 95% completed. Ventilation System installation 50% completed. Airfreight no. 8 arrived to site. Wiring Device installation 95% completed. HV Cable Termination Installation 100% completed LV Cable installation in Hai Van S/S 100% completed 110 kV Transmission Line stringing 100% completed. Test on completion 25% completed. From
Contractor The Contractor is continuing with civil/architectural finishing and repair works on the OCC building. This work is months behind schedule and no concerted effort on the part of the sub-contractor to complete outstanding items. The air conditioning installation is still not complete. HV and MV cable installation is complete but high potential testing still not done due to Contractor failure to provide information on manufacturers recommendations. LV cable installation was 99% complete. All significant electrical equipment items were installed by end of September with the exception of one control/monitoring panel for the 110kV GIS. The OPGW wire. Installed on the transmission line from Tower No. 1 to Tower No. 14 was completed and the fibre cable into the OCC was completed The transition yard steel erection is complete and surge arresters installed. Work began on transition yard earthing and perimeter wall. Test and
commissioning began with the GIS high voltage test and continued with
scheduled tests on the GIS and the Control Room MicroSCADA. The Contractor
schedule is for commissioning completion late November. This does not
include V.O. No. 1 works. At the end of October it appears that commissioning
may be completed, but with outstanding items, in late November. This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||