As of October 31, 2003

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

21 December 2001

Contract period

540 days (Until June 20, 2003)

Time Elapsed (days)

670 of 540 (124.07%) Extend 90days from June 20, 2003

Progress

 

110/22 kV Substation

Continue the civil work & finishing work for OCC Building.

110 kV Transmission Line

Start testing and commissioning

Photographs

110/22kV Substation Operation and Control Center Building
Water Proofing on the Roof of OCC Building
22kV GIS Testing
Equipment in 110kV Power Transition Yard

Top

Construction Supervision

From Consultant Engineer

Painting inside the building 85 % completed.

Floor granite tiles tile 100 % completed.

Door installation 100% completed.

Window installation 100% completed.

Water proofing work on the roof 100% completed.

Air-condition installation 95% completed.

Ventilation System installation 50% completed.

Airfreight no. 8 arrived to site.

Wiring Device installation 95% completed.

HV Cable Termination Installation 100% completed

LV Cable installation in Hai Van S/S 100% completed

110 kV Transmission Line stringing 100% completed.

Test on completion 25% completed.

From Contractor

The Contractor is continuing with civil/architectural finishing and repair works on the OCC building. This work is months behind schedule and no concerted effort on the part of the sub-contractor to complete outstanding items. The air conditioning installation is still not complete. HV and MV cable installation is complete but high potential testing still not done due to Contractor failure to provide information on manufacturers recommendations. LV cable installation was 99% complete. All significant electrical equipment items were installed by end of September with the exception of one control/monitoring panel for the 110kV GIS.

The OPGW wire. Installed on the transmission line from Tower No. 1 to Tower No. 14 was completed and the fibre cable into the OCC was completed The transition yard steel erection is complete and surge arresters installed. Work began on transition yard earthing and perimeter wall.

Test and commissioning began with the GIS high voltage test and continued with scheduled tests on the GIS and the Control Room MicroSCADA. The Contractor schedule is for commissioning completion late November. This does not include V.O. No. 1 works. At the end of October it appears that commissioning may be completed, but with outstanding items, in late November.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination