As of November 30, 2002

Physical Progress

Contractor

JV of Thang Long and Truong Son

Commencement of the Works

1st July 2001

Time Elapsed (days) 515 of 900 (57.22%)
Progress  

North Approach

Continue the embankment work

Lang Co Bridge (867m)

Total 169 nos of bored piling completed up to present. P16, 20, 24, 25 are under construction. 

South Approach

Embankment finished up to 1,000m3

Photographs

Lang Co bridge view
Access road to P7 and P8 have been cleared
Footing excavation of P9
Construction of P24 shaft
Construction of P25 bored pile
Construction of P25 bored pile
Grout injection into ducts - PCI girder
Pouring concrete girder at casting yard No. 1
Instrallation of floating system

Top

Construction Supervision

Summary 

Project schedule has already past 17 months and remaining 13 months now.  Percent completion is 21% based on the activities completion

  • Bored Piling

Total 248 nos. of bored piles are required for foundation.

168 nos. of bored piles has completed and remaining 80 nos.  Percent completion of bored piling is 68%.  3 foundations are under construction of piling work and 7foundations such as north abutment, P1, P2, P3, P4, P5 and P6 are remaining piling work.
  • Substructure

2 abutments and 25 piers are required for Lang Co Bridge.

8 piers have completed up to cross head such as P7, P8, P14, P17, P18, P21, P22 and P23.

8 piers and 1 abutment are under construction of structure work such as P9, P10, P11, P12, P13, P15, P19, P24 and South abutment.

  • Superstructure

Superstructure is not commenced yet.

  • Approach Road

Approach Road road is under construction and South approach road is finished embankment.

  • Girder Production

Total 130 nos. of PCI girders are required production.

2 places of girder production yard are under operation and 47 nos. of PCI girders has completed production.  Percent completion of girder production is 36%.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination