Welcome to Our Site!
 

As of October 31, 2002

Physical Progress

Contractor

Matsushita - Itochu Consortium

Commencement of the Works

13 March 2002

Time Elapsed (days) 228 of 1080 (21.11%)

Progress

  Prepare the mobilization and site establishment
  Modificaton of Ventilation System

 

Photographs

Top

Construction Supervision

Coordination meetings have been held with Package IV Contractor to clarify the operation of the water supply system but at the moment agreement of the system. P.I.D. is still not completed. Discussions have taken place on the electrical interfaces and requirements of Package IV for accommodation of consoles and cables in the control building. The possibility of moving the High level reservoir is under review.

  • Construction schedule for Coming Month

Permanent work schedule

- Arrange the materials for piping under the pump room and prepare application for approval by the Engineer/Employer.

- Prepare more detailed information for studying our proposal for change of water catchment sauce and relocation of the high level reservoir.

- Provide proposal for modification of the existing water supply & water treatment system

- Proceed with contract negotiation with the Vietnamese Sub-Contractor

- Shop drawing for the ventilation equipment.

- Mobilize key personnel to the tentative office in Danang and prepare site establishment.

Temporary Work

- Study the site office establishment and storage facilities

- Make up a Master List for the equipment to be imported to Vietnam.

Top

Previous month / Next month

This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination