Welcome to Our Site!
 

 

As of July 31, 2002

Physical Progress

Contractor

JV of Hazama and Cienco 6

Commencement of the Works

1st October 2000

Time Elapsed (days) 669 of 1460 (45.8%)

Progress

Main Tunnel(3857m)

+ 153.2m - 1402.0m (36.35%)

Evacuation Tunnel(3857m)

+ 180.6m - 1376.7m (35.69%)

Ventilation Tunnel(1810m)

+ 135.8m - 1149.0m (65.56%)

Others

 

Photographs

North Portal - July 2002
Ventilation Adit Portal - July 2002
Joint Survey of the Sliding form No.2 for standard section of Main Tunnel lining concrete
Shifting to Portal at Main Tunnel
Concreting works for standard section of Main Tunnel Lining at Block No.52 Station (2+303.5 (660.5m from Portal)
Water Proofing works and cutting/covering of Rock Bolt Heads at Main Tunnel Sta 2+400 (Junction at Pedestrian C.P. No.2)
Shotcrete praying around the cutting face of Main Tunnel after mucking
Station Survey at Main Tunnel

Drilling for blasting at Evacauation Tunnel at Sta. 3+012.8

Hard rock condition - Rock classified as Class A

Mucking works at Evacuation Tunnel
Dry condition/no water seepage and hard rock on cutting face at Venntilation Adit up to Sta 0+613.8
Tunnel face drilling at Ventialtion Adit
Loading of explosive at Ventilation Adit cutting face
Batching Plant on Site

 

Top

Construction Supervision

Summary

Main Tunnel

  • Excavation

In the month of July, the rock condition encountered in the Main Tunnel was generally good. Geologically, the condition was stable on Class B. On some portion, it was almost classified as class A this month.

Total lengths of 153.20m (station 2+891.8 ~ 3+045.0) were excavated in the Main Tunnel this month, giving a total length of 1,402.00m (Progress: 36.35%) from the tunnel portal.

This month, the excavation of Main Tunnel was improved comparing to previous month's, although the frequent breakdown of equipment continuing but the Chief Resident Engineer continues pushing the contractor to improve and increase the equipment and maintaining to reduce and catch up of the delayed progress previous months.

Niche Excavation:

Twenty-four (27) Niches - Seven (7) Emergency Call Niches and Twenty (20) Firefighting Niches - in the Main Tunnel were already excavated. Excavation of niches continued according to the design niche distribution plan.

Layby

The Layby Left No.1 & 2 and Layby Right No.1 in the Main Tunnel, which has a total length of thirty-two (32) meters each Layby, were completely as per original plan

  • Behind Works (Behind Tunnel Excavation)

The pouring of Class D concrete for the Foundation Beams of the Lining Concrete continued this month. The placing of concrete continued from Station 2+315.5 to 2+451.5 on both sides with a total length of 135.5m on each side.

Installation of Mole Drain Pipes, together with filter cement aggregate, on both sides of the tunnel continued simultaneous with the foundation beams.

Cutting of Rock bolt heads and installation of geo-textile covers were continued on areas with random/safety rock bolts.

Installation of EVA Waterproofing Membrane also continued following the covering of random rock bolts. The completed laying/installation of membrane reached to station 2+422, totaling a length of 758m. The Engineer continued to require testing of the welded joint sheets using air pressure test, as per procedure stated on method statement, prior to continuation of the installation.

Pouring of Concrete Lining also continued as per design segment approved. The Engineer carefully checked, during the joint survey with the contractor, the setting of the form for both bulkhead sides and the thickness as per design requirements.

The Concrete Lining for Standard Section of the Main Tunnel completed until the end of this month totaled to 588 meters, from Segment No. 2 to No. 27 (Sta. 1+665 to Sta. 1+977) and from Segment No. 30 to No. 52 (Sta. 2+027.5 to Sta. 2+303.5). The completed Concrete Lining includes nine (9) Fire Fighting Niches and three (3) Fire Fighting with Emergency Call Niches.

The Concrete Lining of Layby Left No. 1 in Main Tunnel, totaling a length of 31m on station 1+984.5 ~ 2+015.5m, including one (1) Fire Fighting with Emergency Call Niche, was also completed.

The Main Tunnel Concrete Lining completed up to this month totaled to 619m (Progress: 16.05%).

For the Pedestrian Cross Passage No.1, only the concrete lining for the block connected to the Main Tunnel, which has a length of 4.1m, was completed

Evacuation Tunnel

For the Evacuation Tunnel, the rock condition encountered was as good as the Main tunnel condition. Generally, the classification of rock was steady on class B and some portion was classified as class A.

This month the performance of the blasting was still constant to more than three meters per round.

The excavated tunnel length for the month of June 2002 was 180.6m (station 2+839.1 ~ 3+019.7), giving a total length of 1,376.7m (Progress: 35.69%) from the tunnel portal.

The Temporary Transformer Niches No. 1~6 were completely excavated as per approved plan submitted by the contractor.

The Enlarged Pedestrian Cross Passageway Nos. 1 and 2 has been completed.

The Vehicular Cross Passage No.1 was excavated from Evacuation tunnel and Main Tunnel side with a total length of 19.4m also completed.

The ventilation system for Evacuation Tunnel has been transferred through Vehicular Cross Passage No. 1. The relocation has improved the ventilation inside the tunnel. Wasted air coming from the Main tunnel was still eliminated out through Vehicular Cross Passage No. 1 and then through the Evacuation Tunnel.

Ventilation Adit

For Ventilation Adit Tunnel, after passing through ground with bad condition, the rock encountered this month of July 2002 was in a very good condition - totally dry and hard rock. The rock was classified on class B to A. On some cutting face, it was almost classified as class A this month.

The excavated length for the month of June was 135.80m (station 0+739.3 ~ 0+603.5), totaling to 1,149.01m (Progress: 65.56%) from the tunnel portal.

Ventilation Adit - Outside Works

Assembling of the Sliding Form No. 2 for Standard Section of Concrete Lining in Main Tunnel was completed on the month of July 2002 and shift to Portal at Main Tunnel.

Major Events and Issue

 

Activities for Coming Month

  • Permanent works

Main Tunnel Excavation
Main Tunnel excavation will be continued and expected total tunnel length excavation until end of August 2002 is 1,485 meters from the tunnel portal.

Evacuation Tunnel Excavation
Evacuation Tunnel excavation will be continued and expected total tunnel length excavation until end of August 2002 is 1,502 meters from the tunnel portal.

Concrete Lining Works
Construction of Concrete Lining Works at the Main Tunnel will be continued and expected constructed length until end of August 2002 is 823 meters.

Niche Excavations
Three (3) Niches are schedule to be excavated during the month of August 2002.

Drainage Works
Mole Drain construction for Drainage Works inside the Main Tunnel will be continued and expected length of installation will be 1,909 meters until end of August 2002.

Foundation Beam at Main Tunnel
Construction of Foundation Beam for Concrete Lining Works at the Main Tunnel will be continued and expected constructed length until end August 2002 is 1,909 meters.

Waterproofing Works at Main Tunnel
Installation of Waterproof Membrane will be continued throughout the month of August 2002 and expected length of installation is 907 meters.

Electrostatic Precipitator Excavation
Start for the excavation of Electrostatic Precipitator will be on August 19, 2002 and expected length of excavation until end of August 2002 is 50 meters.

Ventilation Adit Excavation
Ventilation Adit excavation will be continued and expected total tunnel length excavation until end of August 2002 is 1,262 meters from the tunnel portal.

Pavement works at the Access Road Works to Ventilation Adit portal is schedule on the 2nd week of August 2002.

  • Temporary Work

a) Continuous operation of the Waste Water Treatment Plant.

b) Operation & Maintenance of Primary Water Control System.

c) Operation of Primary Control System in Main Tunnel, Evacuation Tunnel and Ventilation Adit will be continued.


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination