![]() |
|||||||||||||||||||
Welcome to Our Site! |
|||||||||||||||||||
Progress Report > Package IA - North Tunnel Section
Summary As of June 25, 2002, total length of Main Tunnel Excavation has reached to Sta. 2+870.9 or 1,217.9 meters (including three (3) Layby) form the Tunnel Portal. Twenty three (23) niches (6 emergency & call niche and 17 firefighting niches) and three layby (2 at left side and 1 at right side) were completely excavated inside the Main Tunnel. Concreting of the Foundation Beam and Concrete Lining Works at the Main Tunnel were carried out. As of June 25, 2002 Concrete Lining construction has reached to 451 meters. As of June 25, 2002 total length of Evacuation Tunnel excavation ha reached to Sta. 2+ 828.8 or 1, 175.8 meters from the Tunnel Portal. Three (3) Cross Passageways were completely excavated across the Evacuation and Main Tunnels. As of June 25, 2002 total length of Ventilation Adit Excavation has reached to Sta. 0+759.5 or 990.0 meters from the Tunnel Portal. Main Tunnel
For the month of June, the rock condition encountered in the Main Tunnel was classified as Class B until the end of the month. The small fracture zone observed from last month continued until 26th of this month and some slickenside rock appeared, so the Engineer instructed some safety rock bolts. Geologically, the rock condition was almost good. A total length of 128.50m (station 2+763.3 ~ 2+891.8) were excavated in the Main Tunnel this month, giving a total length of 1,238.8m (Progress: 32.12%) from the tunnel portal. This month, the excavation of Main Tunnel was shorter compare to previous month's progress due to frequent breakdown of equipment almost every shift. The Chief Resident Engineer discussed and strongly pushed the contractor to improve and increase the equipment to catch up with the delayed progress.
Twenty-four (24) Niches - Six (6) Emergency Call Niches and Eighteen (18) Firefighting Niches - in the Main Tunnel were already excavated. Excavation of niches continued according to the design niche distribution plan.
The Layby Left No.2 in the Main Tunnel, which has a total length of thirty-two (32) meters between Sta 2+784 to 2+816, was excavated from 5th to 13th of June 2002, having the same good rock condition as the rest of the Main Tunnel length excavated this month.
The pouring of Class D concrete for the Foundation Beams of the Lining Concrete continued this month. The placing of concrete continued from Station 2+183.5 to 2+315.5 on both sides with a total length of 132m on each side. Installation of Mole Drain Pipes, together with filter cement aggregate, on both sides of the tunnel continued simultaneous with the foundation beams. Cutting of Rock bolt heads and installation of geo-textile covers were continued on areas with random/safety rock bolts. Installation of EVA Waterproofing Membrane also continued following the covering of random rock bolts. The completed laying/installation of membrane reached to station 2+263, totaling a length of 599m. The Engineer continued to require testing of the welded joint sheets using air pressure test, as per procedure stated on method statement, prior to continuation of the installation. Pouring of Concrete Lining also continued as per design segment approved. The Engineer carefully checked, during the joint survey with the contractor, the setting of the form for both bulkhead sides and the thickness as per design requirements. The Concrete Lining for Standard Section of the Main Tunnel completed until the end of this month totaled to 444 meters, from Segment No. 2 to No. 27 (Sta. 1+665 to Sta. 1+977) and from Segment No. 30 to No. 40 (Sta. 2+027.5 to Sta. 1+159.5). The completed Concrete Lining includes seven (7) Fire Fighting Niches and two (2) Fire Fighting with Emergency Call Niches. The Concrete Lining of Layby Left No. 1 in Main Tunnel, totaling a length of 31m on station 1+984.5 ~ 2+015.5m, including one (1) Fire Fighting with Emergency Call Niche, was also completed. The Main Tunnel Concrete Lining completed up to this month totaled to 475m (Progress: 12.32%). For the Pedestrian Cross Passage No.1, only the concrete lining for the block connected to the Main Tunnel, which has a length of 4.1m, was completed. Evacuation Tunnel In the Evacuation Tunnel, the condition of the rock encountered was generally good, although at some times we had experienced water seepage on the excavation face. Geologically, the rock condition was stable on class B ~ A. On some portions, it was almost classified as class A this month. The performance
of the blasting was still constant to more than three meters per round.
The excavated
tunnel length for the month of June 2002 was 98.8m (station 2+740.3
~ 2+839.1), giving a total length of 1,186.1m (Progress: 30.75%) from
the tunnel portal. The Enlarged
Pedestrian Cross Passageway Nos. 1 and 2 has been completed. The ventilation system for Evacuation Tunnel has been transferred through Vehicular Cross Passage No. 1. The relocation has improved the ventilation inside the tunnel. Wasted air coming from the Main tunnel was still eliminated out through Vehicular Cross Passage No. 1 and then through the Evacuation Tunnel. Ventilation Adit Since the beginning of June 2002, water seepage was observed flowing out of drilling holes on almost every cutting face of the Ventilation Adit. On June 5, 2002, anomalous heavy water with a discharge of more than 1.0m3/min spouted out on a high pressure while drilling holes for blasting on the right hand part of the cutting face on Sta. 0+791.5. To observe the water condition ahead of the cutting face, the Chief Resident Engineer made an instruction to drill exploratory holes on the right side wall behind the cutting face, Sta. 0+791.5. Six (6) exploratory holes, each has a length of 10m and angled 30 degrees from the wall were drilled on Station 0+794. When the exploratory holes were drilled, the heavy water spouting out of the cutting face on Sta. 0+791.5 suddenly vanished and reappeared on the exploratory drill holes so the Contractor was able to excavate another round with a length of 2 meter. However, after reaching Sta. 0+789.5, water intrusion with high pressure was experienced on the cutting face again. The Engineer instructed once more to drill one (1) exploratory hole on the center part of cutting face and found out that soft rock was anticipated 1m ahead of the cutting face. Therefore, the Chief Resident Engineer immediately instructed to change the supporting system from type I to type III with the installation of IBO forepoling, wiremesh, 10cm-shotcrete and swellex-type pattern rock bolts. The soft rock, which was classified as Class CII to CI, has weathered zone many joint systems with white clay and its color was mainly gray to white. The contractor carefully continued the excavation using backhoe breaker and not by blasting on the soft ground weathered zone. In the course of the excavation on soft ground area, big amount of water, with a total discharge of 1.2m3/min, spouted out of caves on the left part of the crown. The soft ground weathered zone was experienced until 21st of June 2002. On the
exploratory hole drilling to investigate the rock condition ahead,
which was conducted on Sta. 0+769.3, it was observed that the condition
of the rock ahead would become hard. Hence, the support type III was
changed to type II from station 0+765, however, for one round only.
The rock condition suddenly changed and became totally good so the
Engineer issued an instruction to change the supporting system to
type I from station 0+762 and the said supporting system was applied
until the end of this month. Because of the several problems caused by anomalous water seepage in Ventilation Adit, the Engineer discussed and recommended to PMU 85, client representative, to do the grouting curtain on all areas that have anomalous water seepage. The Engineer anticipated that more suspension of excavation works due to water seepage could happen during the rainy season. The PMU
and MOT delegation finally schedule an inspection in Ventilation Adit
and a general meeting among MOT, the Engineer and the Contractor in
Hanoi on July 2002. Ventilation Adit - Outside Works The assembling of the Sliding Form No. 2 for Standard Section of Concrete Lining in Main Tunnel was started this month. Major Events and Issue Safety Assembly/Meeting
Site Visits of MOT Vice-Minister
Activities for Coming Month
Main Tunnel excavation will be continued and expected total tunnel length excavation until end of July 2002 is 1,397 meters from the tunnel portal. Evacuation Tunnel excavation will be continued and expected total tunnel length excavation until end of July 2002 is 1,358 meters from the tunnel portal. Construction of Concrete Lining Works at the Main Tunnel will be continued and expected constructed length until end of July 2002 is 643 meters. Three (3) Niches are schedule to be excavated during the month of July 2002. Mole Drain construction for Drainage Works inside the Main Tunnel will be continued and expected length of installation will be 1,525 meters until end of July 2002. Construction of Foundation Beam for Concrete Lining Works at the Main Tunnel will be continued and expected constructed length until end July 2002 is 1,573 meters. Installation of Waterproof Membrane will be continued throughout the month of July 2002 and expected length of installation is 740 meters. Ventilation Adit excavation will be continued and expected total tunnel length excavation until end of July 2002 is 1,133 meters from the tunnel portal. Access Road Works at the Ventilation Adit will continued.
Continuous operation of the Waste Water Treatment Plant. Operation & Maintenance of Primary Water Control System. Operation of Primary Control System in Main Tunnel, Evacuation Tunnel and Ventilation Adit will be continued. Dewatering inside the three tunnels will be continued. Installation and Operation of Ventilation Systems and Lighting System in Main Tunnel, Evacuation Tunnel and Ventilation Adit will be continued. Maintenance and Operation of all equipments will be continued. Maintenance
of Contractor's office & camps will be continued. This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||