Progress Report > Package IIA - Lang Co Bridge Section
Photographs Summary from Contractor The completion percentage was 99.8% based on the completion of activities (including 80.6% per total 80.6% of bridge work and 19.2% per total 19.4% of road, Toll Plaza work and general requirement work). Material Engineering Main emphasis on material work:
Main emphasis on material work:
Local Road: Embankment is being constructed for all route. Subgrade layer is being completed. In this month, taking over for completed items has been carried out. However, some items must be checked and repaired again. The Engineer has sent the report to the Contractor. This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team |
|
||||||||||||||