Welcome to Our Site!
 

 

As of November 31, 2004

Physical Progress

Contractor

JV of Thang Long and Truong Son

Commencement of the Works

1st July 2001

Contract period

900 days (Until December 31, 2003)

Time Elapsed (days)

1230 of 900 (136.67%)

Progress

Approach Road and Lang Co Bridge (867m)

Completion percentage is 99.8% including 80.6% of bridge work and 19.2 of Road, Toll Plaza and general works.

Photographs

Top

Construction Supervision

Summary from Contractor

The completion percentage was 99.8% based on the completion of activities (including 80.6% per total 80.6% of bridge work and 19.2% per total 19.4% of road, Toll Plaza work and general requirement work).

Material Engineering

Main emphasis on material work:

Construction of Local Road

Taking over for Package 2A

Main emphasis on material work:

Until now, the works of Package has been nearly completed. The remain works are only small work and addition works (such as local road). In this month, road marking item has been completed.

Local Road: Embankment is being constructed for all route. Subgrade layer is being completed.

In this month, taking over for completed items has been carried out. However, some items must be checked and repaired again. The Engineer has sent the report to the Contractor.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination