Construction
Supervision
Project
Schedule passed 25 months and 05 months remained from
the reporting month. Completion percentage was 71% (the
last value was not correct) based on the activities
completion (including 61% of bridge work and 10% of
road, Toll Plaza work and general requirement work).
Bored
piling:
Total
218 nos of bored piles with different diameter are
required for foundation.
214
nos. of bored piles completed and 04 nos.
remained.
Completion
percentage of bored piling is 98.2%.
Foundation
of piers: P2 was under preparation of piling work.
Substructure:
2
abutments and 25 piers are required for Lang Co
Bridge.
19
piers and 1 abutment completed up to cross head such as
P6, P7, P8, P9, P10, P11, P13, P14, P15, P16, P17, P18,
P19, P20, P21, P22, P23, P24, P25 and South
Abutment.
P12
and North Abutment A1 were under construction.
Sheet
piles for pit excavation of P05 is finished. P1, P2, P3
and P4 were under construction.
Superstructure:
Launching
of span 26, 25, 24, 23, 22, 21, 20, 19, 18 and 17
completed.
Concrete
of diaphragm of span above were completed too.
Concrete
cast for Deck slab of those spans was carrying out but
have not completed yet.
Deck
slab of span 26 and 25 completed the casting.
Approach
Road:
Surcharge
fill on North approach road was completed, subgrade
layers and mortar rip-rap were under construction.
South
approach road was completed the embankment.
Toll
plaza:
Embankment
and footing of building were completed.
Toll
plaza building completed generally. Fence of building
was under construction.
Girder
Production:
total
130 nos. of PCI girders were required to produce.
2
places of girders prodction yard were under operation
and 90 nos. of PCI girders completed the
production.
Completion
percentage of girder production was 69%.