As of July 31, 2003

Physical Progress

Contractor

JV of Thang Long and Truong Son

Commencement of the Works

1st July 2001

Contract period

900 days (Until December 31, 2003)

Time Elapsed (days)

753 of 900 (83.67%) Remaining 147 days

Progress

 

North Approach

Surcharge fill under removal

Lang Co Bridge (867m)

Completion of 214/218 bore piles (98.2%). Foundation of Piers: P2 under preparation of piling work

South Approach

Embankment completed

Photographs

General Sight View of Lang Co Bridge
Construction of A1: Complete
Construction of P5: Base
Construction of P12 Pier: Transverse Block
Construction of P12: Completed
Lauching Girder: Span No.18
Construction of Span No.23, 22, 21
Construction of Superstructure of Span 25
General Sight View of Girder on Site
Construction of Box Culvert at Sta. 0+266
Construction of Toll Plaza Building
Constructed Guard Fence of Toll Plaza

Top

Construction Supervision

Project Schedule passed 25 months and 05 months remained from the reporting month. Completion percentage was 71% (the last value was not correct) based on the activities completion (including 61% of bridge work and 10% of road, Toll Plaza work and general requirement work).

Bored piling: 

Total 218 nos of bored piles with different diameter are required for foundation. 

214 nos. of bored piles completed and 04 nos. remained. 

Completion percentage of bored piling is 98.2%. 

Foundation of piers: P2 was under preparation of piling work.

Substructure: 

2 abutments and 25 piers are required for Lang Co Bridge. 

19 piers and 1 abutment completed up to cross head such as P6, P7, P8, P9, P10, P11, P13, P14, P15, P16, P17, P18, P19, P20, P21, P22, P23, P24, P25 and South Abutment. 

P12 and North Abutment A1 were under construction. 

Sheet piles for pit excavation of P05 is finished. P1, P2, P3 and P4 were under construction.

Superstructure: 

Launching of span 26, 25, 24, 23, 22, 21, 20, 19, 18 and 17 completed. 

Concrete of diaphragm of span above were completed too. 

Concrete cast for Deck slab of those spans was carrying out but have not completed yet.

Deck slab of span 26 and 25 completed the casting.

Approach Road: 

Surcharge fill on North approach road was completed, subgrade layers and mortar rip-rap were under construction. 

South approach road was completed the embankment.

Toll plaza: 

Embankment and footing of building were completed. 

Toll plaza building completed generally. Fence of building was under construction.

Girder Production: 

total 130 nos. of PCI girders were required to produce. 

2 places of girders prodction yard were under operation and 90 nos. of PCI girders completed the production. 

Completion percentage of girder production was 69%.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination