Bored
Piling
Total
248 nos. of bored piles are required for foundation.
182
nos. of bored piles has completed and remaining 66
nos. Percent completion of bored piling is 73%. 1
foundation is under construction of piling work and
7 foundations such as North Abutment, P1, P2, P3,
P4, P5 and P6 are remaining piling work.
Substructure
2
abutments and 25 piers are required for Lang Co Bridge.
11
piers and 1 abutment have completed up to cross head
such as P7, P8, P9, P14, P17, P18, P21, P22, P23,
P24, P25 and South Abutment.
7
piers are under construction of structure work such
as P10, P11, P12, P13, P15, P16 and P19.
Superstructure
Preparation
of launching at south abutment has just commenced
on 10 February 2003.
Approach
Road
North
approach road has completed for surcharge fill and
South approach road is finished embankment.
Girder
Production
Total
130 nos. of PCI girders are required production.
2
places of girder production yard are under operation
and 52 nos. of PCI girders has completed production. Percent completion of girder production is 40%.