Progress Report > Package IA - North Tunnel Section Form No.2 Second Lift Center Wall Completion Assembling at Ventilation Adit for Csting Concrete Starting Sta. 0+471.63~ 0+483.59 Block No. 74; L=11.96m Đặt khuôn bê tông thứ 2 tường phân cách, Hầm thông gió
|