Form No.2 Second Lift Center Wall Completion Assembling at Ventilation Adit for Csting Concrete Starting Sta. 0+471.63~ 0+483.59 Block No. 74; L=11.96m

Đặt khuôn bê tông thứ 2 tường phân cách, Hầm thông gió

Tháng 03/2004 - Trở về