Haivan Pass Tunnel
CONSTRUCTION PROJECT

Home | | Sitemap | Guestbook | Contact us

Welcome to Our Site!

 

Progress Report > Package III- Electrical Works

As of August 2003 - Home | Home

Grouting Measurement at EP1

Đo lường phun vữa tại Hầm lọc bụi tĩnh điện số 1

Tháng 08/2003 - Trở về


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 

2002/HVTP Webmaster