Haivan Pass Tunnel CONSTRUCTION PROJECT
Progress Report > Package IA - North Tunnel Section
As of January 2004 - Home | Next
EP No.2 Lining Concrete Connection to MT & Continuing Casting L/C up to Block No.6 Sta. 0+041.72
Bê tông vỏ hầm lọc bụi tĩnh điện số 2 đoạn nối với hầm chính
Tháng 01/2004 - Trở về This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
Tháng 01/2004 - Trở về
This homepage is presented by the Consultant Team
Any further question should be forwarded to Webmaster or Consultant Team