As tunnel pass nears completion, contractor looks to other projects
(Date:
November 11, 2004. Source: Vietnam News)

|
Installing
the ventilation system at the Hai Van Tunnel. — VNS Photo
Thanh Hai
|
DA
NANG — Workers and engineers, close to finishing the new Hai Van
Tunnel Pass, already have their eyes on future projects.
The
employees of the Civil Engineering Construction Corp. No. 6 (CIENCO 6)
expect to complete the mountain tunnel pass later this year.
"A
large number of Cienco 6’s engineers and workers are expected to take
part in other projects to be undertaken by Hazama," reported deputy
director of the Hazama - Cienco 6 joint venture, Tran Thanh Minh.
The
head of the Japanese Hazama Company in Viet Nam, Hideo Matsumoto, held a
press conference on Saturday to announce that the construction of the
northern section of the tunnel is nearing completion and will be
transferred to the project owner on December 15.
Possible
Official Development Assistance (ODA) funded projects to be taken on by
Hazama in the future may include the Dai Ninh hydro-electric power plant
in Lam Dong Province, Ta Trach hydro-electric plant in Thua Thien-Hue,
and the Thu Thiem Underground Tunnel in HCM City.
The
Hai Van Tunnel Pass contract, won by Hazama-Cienco 6, consists of a
3,857m long 80sq.m main tunnel, a 3,857m long 15sq.m evacuation tunnel,
seven cross-passageways, and nearly 2,000m long ventilation ducts.
"We
could say that we have brought the northern section of the tunnel
project to a successful completion," said Matsumoto. "The
project’s success will help strengthen the co-operative links between
Hazama and Cienco 6 and at the same time promote co-operation between
Japan and Viet Nam."
Director
of the Hazama - Cienco 6 Joint venture, Masashi Kuroda, said they first
encountered difficulties after digging just 400 metres. Underground
water overwhelmed the tunnel, forcing them to pump out 2 million cu.m of
water.
In
April 2003, the joint venture encountered difficulties when the owner of
the project — the Ministry of Transportation — demanded that the two
sections of the tunnel be linked by October of last year.
Kuroda
said they had to dig and then pave 158 metres of the tunnel every month
to reach their target.
Due
to the vast experience gained from working on the site, about 50
Vietnamese staff have been appointed to positions previously held by
engineers from Thailand, Indonesia and the Philippines.
Hazama
has also transferred the operation of the tunnel and technology
management into Vietnamese hands.
Hazama
entered Viet Nam in 1961 and has taken part in more than 100 projects.
Among them, Matsumoto said, are the Da Nhim Hydro Power Plant and Cho
Ray Hospital, adding that these are "the most successful projects
funded by ODA loans."
"It’s
a great honour for us to undertake the Hai Van Tunnel Project, as it is
the largest tunnel in Southeast Asia and a landmark in the history of
Viet Nam’s transportation sector," said Hazama head, Matsumoto.
The
tunnel project required an investment of US$251 million; 85 per cent of
the capital came from ODA and was provided by the Japanese Bank for
International Co-operation. Located about 1,000km north of HCM City,
some 2,500 vehicles used the pass each day in 1998, and this figure is
expected to rise to 7,000-8,000 vehicles per day by 2005.
The
project will turn the 21-km pass into a 12-km road and tunnel complex.
Despite
the project’s success, Hazama - Cienco 6 administrators complained of
some local workers’ weaknesses.
In
addition to the 200 engineers and workers from Cienco 6, the project had
to sign labour contracts with 500 unskilled workers.
According
to deputy director Minh, these newly recruited workers’ lack of skill
and unruliness caused management troubles.
He
added that these poorly trained workers would not be eligible for future
employment opportunities when the Hai Van Pass Tunnel becomes
operational in May 2005. — VNS
Top
This
homepage is presented by the Consultant Team
Any
further question should be forwarded to Webmaster
or Consultant Team