Hai Van tunnel
in the Central is under way of construction
Date:July
01, 2003
The deputy
general director of project management board, Nguyen Ngoc Canh released
that the project of Hai Van tunnel is under way of construction with
drilling of 5,160 meters (up to July 1) over total main tunnel of 6,200
meters, including the whole ventilating lines and 2,400m in the south
of the tunnel . In northern part of the tunnel, only a part of 2,760
meters was completed due to discovering some under ground water.
All efforts
now are focused on the northern part to drill the remaining part of
1,040 meters. Other jobs on the project are also going under the same
pace. The constructing units ensure to reach quality and the speed of
the project with 10-12 metres of drilling per day. (VN Economy)