Hai
Van tunnel back on track
Date:
November 01, 2002
Construction
of the US$250M, 6.3km long Hai Van Pass road tunnel in central Vietnam
is back on schedule following the the successful remediation of the
collapse last year (T&TI January 2002).
The bench and invert excavations are now virtually complete, ready for
the main tunnel lining to start as T&TI went to press as
originally planned. The tunnelling works should be completed in 2003.
The project
includes a 6.3km long, 90m2 tunnel section beneath the Hai Van massif
with a parallel 16m2 evacuation tunnel.
Construction
is predominantly through good quality granite by NATM. However, the
first 100m at each portal is composed of highly weathered granite with
erosion deposits covering the valley floors.
Tunnelling
began in mid 2001 from both the North and South portals, but only progressed
30m from the South portal in the soft ground section of the main tunnel
when a major collapse occurred.
A cross
passage was then constructed in good rock from the progressing evacuation
tunnel. This allowed construction to resume on schedule and left the
soft ground section to be completed off the critical path.
The pilot
tunnel broke through in April 2002, with breakthrough of the full top
head-ing on 4 July 2002. Tunnel excavation is now progressing on all
tunnel faces with advance rates of 120m-180m per month.
Problems
were also encountered in the ventilation adit, where higher than expected
water inflows were encountered in fault zones. This led to the delay
of approximately 6 weeks. Remedial grouting works are currently being
finalised.
The two
tunnelling contracts were awarded in September 2000. The Hazama and
Cienco 6 JV won the North section, while the Dong Ah and Song Da JV
won the South section.
(Source:
Tunnels and Tunnelling International)
Top
This
homepage is presented by the Consultant Team
Any
further question should be forwarded to Webmaster
or Consultant Team