Hai Van Pass
tunnel makes solid progress
(Date:July
15, 2002. Source: Vietnam News)
HA NOI
The construction of a tunnel through Hai Van Pass in central
Viet Nam is progressing smoothly and is well on course for its scheduled
completion next year.
The project
includes a main tunnel and a rescue tunnel, with a length of 6.4 km
long, from Lang Co in Phu Loc District of the central province of Thua
Thien-Hue to the Lien Chieu Industrial Zone in Da Nang city.
By June
end, 2,095 m of the main tunnel and 2,246 m of the rescue tunnel was
dug, or one third of its total envisaged span.
Construction
is being undertaken by Japans Hazama and Viet Nams Civil
Engineering Corporation (CIENCO 6) at the northern end, and the Republic
of Koreas Dong Ah and the local Song Da Construction Corporation
at the southern end.
The main
tunnel is 11.5m wide and has two lanes that will permit vehicles to
ply at 80 km an hour; the rescue tunnel runs alongside and is connected
to it by branches, spaced at 400m intervals.
The 1,032
billion VND (73.7 million USD) project is funded by the State exchequer
and loans from the Japanese Bank for International Co-operation and
is the countrys first road tunnel to receive technical and financial
assistance from international financial organisations.
Once completed,
the Hai Van tunnel is expected to improve traffic in the area as well
as in the Asian sub-region. VNS