Around
the loosen soil problem at Hai Van Pass Tunnel
Date:
April 04, 2002
At
10 am on April 2, 2002 we are at South Portal of Hai Van Pass Tunnel.
It is such a blazing hot day that the area where the machines and equipment
located in front of the portal is scorching and shining aching the eyes.
Many grass squares turn yellow.
Discussing
with Mr. Thai Son, Deputy Project Manager of Package 1B Hai Van Tunnel
Construction Project (Joint Venture of Dong Ah -Korea and Song Da Incorporation),
we are informed that inside main tunnel the construction unit reach
loosen mud on drilling to meter 29. Because groundwater ejects so hard,
loosen mud streams out, which is easy to cause cave-ins, that's why
it is a must to tighten the tunnel width from 12m to 3.8m and height
from 7.8m to 4.2m, to lead loosen mud and groundwater outside. This
conducting tunnel has been 48m long. Mr. Thai Son also discloses that
after the cave-in during the construction in rainy season September
2001, the construction team used wire mesh and shotcrete lining to cover
the hole; at the same time used a big quantity of rocks and soil to
lean on the tunnel face preventing rock and soil from coming out through
groundwater, making the subsidence area stable for excavation continue.
But after that when they reached loosen mud, a conducting tunnel was
required. The loosen mud out-of-plan trouble takes the construction
company lot of .labor to overcome. Joint Venture of Dong Ah and Song
Da is going to hire contractors of international experience to proceed
the construction of expanding the conducting tunnel to main tunnel.
The joint venture has recommended three prestigious tunnel companies
from Japan, Taiwan, and Hong Kong; and they are waiting for the approval
from their superior...
Right
on site of South Portal, contacting with us. Engineer Le Van Khang -
Manager of Technology and Design Department of PK1B Management Unit,
adds some more information: Because of the loosen mud in main tunnel,
they concentrate on excavating evacuation tunnel (4.2m long and 4.7m
high), up to now, reaching 622 meter deep. At Station 0+180, they make
a cross passage to main tunnel and find all rock and soil with no loosen
mud, therefore they excavate open to the main tunnel compliant with
the design to the North for 312 meters. So, excluding weak soil part
of 48 meters of conducting tunnel already excavated, and 25 meters of
not yet excavated, the main tunnel excavation is 341 meters (29 meters
from the portal and 312 meters inside). The loosen mud during excavation
slows down the work progress by 4 months; but after overcoming with
cross passages to main tunnel at the area of no loosen mud, there will
be a delay of only 2.5 months compared with the overall schedule. At
this time of sunny and hot weather. Joint Venture of Dong Ah - Song
Da mobilizes more than 600 workers in three shifts for 24/24 hours on
site, pushing the progress, to get through with North Tunnel on October
1, 2004 as planned.
At
the office of Project Management Unit 85 (PMU85), we are informed by
Mr. Nguyen Ngoc Canh - Project Manager: In North Tunnel through Hai
Van Pass, the excavation length is 790 meters for main tunnel and 780
meters for evacuation tunnel. Currently 168 meters of main tunnel lining
was already concreted waiting to be installed lighting equipments. The
length of Ventilation Adit is 720 meters. To South Tunnel, after the
overcome of loosen mud by making cross passage from Evacuation Tunnel
to Main Tunnel from inside, 6 meters is excavated per day and there
is a tendency to catch the progress to finish in time. We raise a question
"Government has agreed for PMU85 to change one part of Hai Van
Pass Tunnel Project, means the enlargement of Evacuation Tunnel to Main
Tunnel, why has there been no commotion so far?". Mr. Canh answers
that the enlargement of Evacuation Tunnel to Main Tunnel can be considered
as a new project, therefore it is waiting for the passing of Japan Bank
for International Cooperation (JBIC), because the investment capital
of USD 251.042 million mainly comes from this unit loan.
(Source:
Cong An Danang)
Top
This
homepage is presented by the Consultant Team
Any
further question should be forwarded to Webmaster
or Consultant Team